220k views
5 votes
Budgeted production 26,000 units Actual production 27,500 units Materials: Standard price per ounce $6.50 Standard ounces per completed unit 8 Actual ounces purchased and used in production 228,000 Actual price paid for materials $1,504,800 Labor: Standard hourly labor rate $22 per hour Standard hours allowed per completed unit 6.6 Actual labor hours worked 183,000 Actual total labor costs $4,020,000 Overhead: Actual and budgeted fixed overhead $1,029,600 Standard variable overhead rate $24.50 per standard labor hour Actual variable overhead costs $4,520,000 Overhead is applied on standard labor hours. The direct materials quantity variance is

User Kingnight
by
8.2k points

1 Answer

4 votes

Answer:

($52,000) Unfavorable

Step-by-step explanation:

The computation of direct materials quantity variance is shown below:-

Direct material quantity variance = (Standard quantity × Standard rate) - (Actual ounces purchased and used in production × Standard rate)

= ($220,000 × $6.50) - ($228,000 × $6.50)

= $1,430,000 - $1,482,000

= ($52,000)Unfavorable

So, for computing the Direct material quantity variance we simply applied the above formula.

User Bers
by
8.5k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.