If it takes 6 men 4 days to dig a hole 3 metres deep, how long will it take 10 men to dig a hole 7 metres deep?

2 Answers

2 votes

Answer:

8 days:)

Explanation:

User Kruczy
by
4.2k points
7 votes
8 days. hope this helps :)
User Gglasses
by
4.8k points