Answer:
More likely: on time
By 0.3 or 30%
Explanation:
Bad weather is column 2
P(delayed) = 17.5/(17.5+32.5)
= 17.5/50 = 0.35
P(on time) = 32.5/(17.5+32.5)
= 32.5/50 = 0.65
0.65 - 0.35 = 0.3