Answer:
Forming rate $ 4.95 per machine hour
Finishing rate $ 9.60 per labor hours
Step-by-step explanation:

The overhead rate is determined by divided the expected cost over the expected volume of the cost driver.
Then, it will e applied based on actual volume of it.
Forming cost driver: Machine Hours
$118,800 / 24,000 machine hours =
$ 4.95 predetermined overhead rate
Finishing cost driver: Labor hours
$57,600 / 6,000 labor hours =
$ 9.60 predetermined overhead rate