Answer:
Mitigated damages term
Step-by-step explanation:
The best defense for Stewarts in this situation is Mitigated damage term. This enables him to reduce his penalty on the breach of contract,
Even though the situation was outside his control , but the contract he signed stipulated that he will pay $50,000/ day of delay in the project which had unfortunately happened.
However , the damages can be reduced or even avoided if he sue for mitigated damage term