Please help, I don’t understand it so explain don’t just put the answer if u can lols

Please help, I don’t understand it so explain don’t just put the answer if u can lols-example-1
User RikRak
by
8.2k points

2 Answers

1 vote

Answer:

80 1/2 days between first and second son

This in days is 1-81 days to finish one house.

Explanation:

1st Son = 45 + 18 + 27 = 90 saved the father 18 days. 27 of 45 = 60% inv 40%

2nd Son = 45 + 9 +36 = 90 saved the father 9 days = 36 of 45 = 80% inv 20%

1st Son 40% needs to be increased 60% to complete house

2nd Son 20% needs to be increased 80% to complete house

1st Son House takes Son 1 in days = 27 x 1.60% = 43.2 + 27 = 60.2

2nd Son House takes Son 2 in days = 36 x 1.80%= 64.8 + 36 = 100.8

60.2+100.8 = 161 days.

=161 days for 2 homes.

= 80 1/2 days for one home.

User Afterburner
by
8.4k points
5 votes

Answer

27 days

Explanation:

father= 45 days

oldest son + father=27 days

youngest + father= 36 days

45-27=18

45-36=9

18+9=27

so it would take 27 days for both sons to complete the house

18 days=oldest son

9 days =youngest son

User ShadowGames
by
8.4k points