A painter can finish painting a house in 7 hours. Her assistant takes 9 hours to finish the same job. How long would it take for them to complete the job if they were working together?

2 Answers

5 votes

Answer:

3.9375 hours

Explanation:

Combined time

= product of individual times ÷ sum

= (7×9)/(7+9)

= 63/16

= 3.9375

User Cesar Morillas
by
8.1k points
1 vote

Answer:

c =3.9375 hours

Explanation:

The formula to determine time to finish the job together is

1/a + 1/b = 1/c

Where a and b are the times to complete the job separately and c is the time to complete the job when working together

1/7 + 1/9 = 1/c

Multiply by 63c to get rid of the fractions

63c*(1/7 + 1/9) = 1/c *63c

9c + 7c = 63

Combine like terms

16c = 63

Divide each side by 16

16c/16 = 63/16

c =3.9375 hours

User Jeff Holt
by
7.5k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories