Answer:
a. 1.5 hours
Step-by-step explanation:
The computation of the standard direct labor hours per unit is shown below:
Standard labor hour per unit is
= Production hours + setup hours + allowance for rest period
= 1.0 hours per unit + 0.2 per hours + 0.3 hours
= 1.5 hours
We simply added the production hours, setup hours, and the allowance for rest period so that the standard labor hour per unit could come