Answer:
$343.75
Step-by-step explanation:
The computation of amount of manufacturing overhead is shown below:-
For computing the amount of manufacturing overhead first we need to find out the predetermined overhead rate which is shown below:-
Predetermined overhead rate = Estimated manufacturing overhead costs ÷ Estimated machine hours
= $550,000 ÷ 8,000
= $68.75 per machine hour
Overhead allocated = Predetermined overhead rate × Machine hours
= $68.75 × 5
= $343.75