Answer:
$4,248 under applied
Step-by-step explanation:
For computing the ending overhead amount we need to do following calculations which are shown below:
Predetermined overhead rate is
= Total estimated manufacturing overhead ÷ estimated direct labor-hours
= $516,368 ÷ 21,880 hours
= $23.6 per hour
Now
Actual overhead applied is
= $23.6 × 21,700 hours
= $512,120
Therefore,
Overhead under applied is
= Manufacturing overhead - Actual overhead applied
= $516,368 - $512,120
= $4,248 under applied