Answer:
The correct answer is 31 customers per day.
Step-by-step explanation:
Consider the current capacity requirement as = x
Management wants to have a capacity cushion = 8%.
So the utilization is required = 100% - 8% = 92%
A process of currently services an average of 43 customers per day and utilization is 90%.
Expected Demand=70%= 70 ÷ 100 = 0.70
Current utilization = 90% = 0.90
Let Capacity requirement = X
Capacity requirement ÷ required utilization = Expected Demand rate × current service rate ÷ current utilization rate
X ÷ 0.92 = 0.70 × 43 ÷ 0.90
X = 0.70 × 43 ÷ 0.90 × 0.92
= 30.76 or 31
Needed capacity requirement is 31 customer per day.