Ernest operates an ice cream stand during the months of may, june, july, and august. ernest's ice cream machine is broken and needs a new part to run. he contracts to have the part shipped to him by special carrier. ernest emphasizes that the part needs to be delivered by april 25 or he will not be able to be open on may 1 as he has advertised. if the shipper fails to deliver the part on april 25, ernest will be able to recover consequential damages caused by the delay.a. true.b. false.

User Aviles
by
6.7k points

1 Answer

4 votes

Answer:

True

Step-by-step explanation:

True, as Earnest has already planned to open an ice cream stand on May 1 for which a new part needs to be delivered to him by the shipper by April 25.

However, the shipper failed to deliver him the same due to which Earnest was not able to open an ice cream stand on May 1.

So, the shipper now has to recover consequential damages caused by the delay as it was a big mistake on the part of the shipper.