Answer:
Therefore based on the decision tree, the value earned of the first option is greater than the second one. then there is no need to increase the staff.
Step-by-step explanation:
From the given question, we set up a decision tree to show whether Softside should increase the size of the project staff.
We will make use of 2 options
First Option
WE run the project with existing staff
The cost of project = 50,000
The cost of delayed project =50,000+ 30,000 = 80,000
0.3 (80,000) EV (delay) = 0.3 * 80,000 = 24,000
Contract
(100,000)
0.7 (50,000)EV (no delay) = 0.7 *50,000 =35,000
EV = The project fixed price - total cost
The total EV 100,000 - (24,000 + 35,000) = 59,000
For the option 2
Increase of staff
The cost of project = 50,000 + 10,000 =60,000
The cost of delayed project = 60,000 = 8,000 = 68,000
0.2 (68,000) EV (delay) = 0.2 * 68,000 = 13,600
Contract
(100,000)
0.8 (60,000) EV (delay) = 0.8 * 60,000 = 48,000
Then,
The total EV 100,000 - ( 13,600 + 48,000)
= 38,400
Therefore based on the decision tree, the value earned of the first option is greater than the second one. then there is no need to increase the staff.