A project has four activities (a, b, c, and

d.that must be performed sequentially. the probability distributions for the time required to complete each of the activities are as follows: activity activity time (weeks) probability a 5 0.25 6 0.35 7 0.25 8 0.15 b 3 0.20 5 0.55 7 0.25 c 10 0.10 12 0.25 14 0.40 16 0.20 18 0.05 d 10 0.60 12 0.40 the attached file, project, contains a spreadsheet simulation model to estimate the average length of the project and the standard deviation of the project length. create 2000 simulation trials. what is the project length? round your answer to one decimal place.

User Morkro
by
3.7k points

1 Answer

3 votes

Complete Question:

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

check the first file attached

Answer:

project length: 35 weeks

Standard Deviation: 2.80 weeks

Step-by-step explanation:

check The second , and third file attached for formatted excel solution

A project has four activities (a, b, c, and d.that must be performed sequentially-example-1
A project has four activities (a, b, c, and d.that must be performed sequentially-example-2
A project has four activities (a, b, c, and d.that must be performed sequentially-example-3
A project has four activities (a, b, c, and d.that must be performed sequentially-example-4
User Plaute
by
3.5k points