Complete Question:
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
check the first file attached
Answer:
project length: 35 weeks
Standard Deviation: 2.80 weeks
Step-by-step explanation:
check The second , and third file attached for formatted excel solution