"Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs using the following sequences: SPT sequence, EDD sequence, and the sequence 4-2-5-1-3. Use minus sign to enter negative lateness values, if any. If your answer is zero, enter "0". Round your answers for the average values to two decimal places.'

User Ajeanson
by
5.1k points

1 Answer

1 vote

Answer:

See explaination

Step-by-step explanation:

SPT is recommended. It minimizes average flow time and number of jobs in system. Note that the last sequence based on common sense or random sequencing is the worst performer on all criteria, so the job sequencing rule does make a significant difference in insurance firm performance.

See attachment for the calculation.

"Compute the flow time, tardiness, and lateness for each job, and the average-example-1
"Compute the flow time, tardiness, and lateness for each job, and the average-example-2
"Compute the flow time, tardiness, and lateness for each job, and the average-example-3