Answer:
40%
Step-by-step explanation:
For computing the manufacturing cycle efficiency, first we have to compute the throughput time which is shown below:
Throughput time = Process time + Inspection time + Move time + Queue time
= 6 + 0.6 + 0.4 + 8
= 15
Now
Manufacturing cycle efficiency (MCE) is
= Value added time (process time) ÷ Throughput time
= 6 ÷ 15
= 40%
We simply applied the above formulas so that the manufacturing cycle efficiency (MCE) could come