Answer:
B) credit to Manufacturing Overhead for $32,000.
Step-by-step explanation:
Total manufacturing overhead = (milling department machine hours + cutting department machine hours) x overhead rate per machine hour = (2,400 + 4,000) x $5 = $32,000.
Since the manufacturing overhead expense is allocated to the asset produced, the expense is credited. Once the product is sold, the expense will become part of the cost of goods sold and they will be debited.