Answer:
The fixed overhead production-volume variance is $9,000 U
Step-by-step explanation:
In this question, we are tasked with calculating the fixed overhead production-volume variance.
We start by calculating the fixed overhead applied to production.
mathematically that is equal to : 54,000 * 0.03 * 50 = 81,000
The budgeted fixed overhead = 90,000
Mathematically,
Fixed overhead production-volume variance = Budgeted fixed overhead - fixed overhead applied to production = 90,000 - 81,000 = $9,000 U