Answer:
71,100
Step-by-step explanation:
The calculation of standard direct labor hours is shown below:-
Labor rate variance = (Actual rate - Standard rate) × Actual hours worked
$35,000 = ($497,000 ÷ 70,000 - Standard rate) × 70,000
(7.1 - Standard rate) = $0.5
= $6.6 per hour
= Labor variance efficiency = (70,000 - Standard hour) × $6.6 per hour
= -$7,260 = (70,000 - Standard hour) × $6.6 per hour
Standard hours = $70,000 + 1,100
= 71,100