Answer:
Throughput for each month is as follows.
Average per Month (in days) 1 2 3 4
Throughput time 5.3 4.9 3.9 3.5
Step-by-step explanation:
Average per Month (in days) 1 2 3 4
Throughput time 5.3 4.9 3.9 3.5
Delivery cycle time (days) 14.9 12.9 8.9 7.5
(MCE) 0.7/5.3 0.7/4.9 0.7/3.9 0.4/3.5
(MCE) % 13.21% 14.29 17.95 11.43
Working
DataSpan, Inc.
Total sales (units) 10,550 10,440 10,560 10,560
Average per Month (in days) 1 2 3 4
Move time per unit 0.6 0.5 0.4 0.8
Process time per unit 0.7 0.7 0.7 0.4
Wait time per order 9.6 8.0 5.0 4.0
Queue time per unit 3.4 3.1 2.4 1.7
Inspection time per unit 0.6 0.6 0.4 0.6
1.a- Throughput (manufacturing cycle) time = Inspection Time + Process Time + Move Time + Queue time
All of the above will be added except wait time.
Throughput time 5.3 4.9 3.9 3.5
Delivery Cycle Time= NonValue Added time + Value Added Time (Process Time)
Non Value Added Time= Wait time + Inspection Time + Move Time + Queue Time ( all of the above would be added)
Delivery cycle time (days) 14.9 12.9 8.9 7.5
Manufacturing cycle efficiency (MCE)=Process Time/ Processing Time + Inspection Time + Move Time + Queue time
(MCE) 0.7/5.3 0.7/4.9 0.7/3.9 0.4/3.5
(MCE) 13.21% 14.29 17.95 11.43