The mouse executive board meeting was drawing to a conclusion; the only way they would be able to detect the presence of the cat was to tie a bell around its tail. Under their risk management identification scheme, this would fall under _______________ risk.

a. commercial
b. execution
c. financial
d. technical

1 Answer

5 votes

Answer:

Technical Risk

Step-by-step explanation:

Technical Risk is the type of risk associated directly with the knowledge base being used and it's technical aspects including such things as understanding, reproducability and the like.That is, risks that involve the application of specific knowledge of the technology for the project to be carried out.