The budget for the month of May was for 11,200 units at a direct materials cost of $19 per unit. Direct labor was budgeted at 28 minutes per unit for a total of $100,800. Actual output for the month was 8,900 units with $137,500 in direct materials and $81,775 in direct labor expense. The direct labor standard of 28 minutes was obtained throughout the month. Variance analysis of the performance for the month of May would show a(n): (CMA adapted)

1 Answer

3 votes

Answer:

Direct labor price(rate) variance = $1,675 (unfavorable)

Direct labor efficiency variance = 0

Step-by-step explanation:

As per the data given in the question,

Number of units = 11,200

cost = $19 per unit

Labor budgeted = at 28 minutes per unit

Total budget = $100,800

Actual output = 8,900 units

Direct material expense = $137,500

Direct labor expense = $81,775

As per the following formula,

Direct labor price variance = (Actual price - Standard price) × Actual hour

= ($81,775 ÷ 8900 × 2 - $100,800 ÷ 11,200 × 2) × 8,900 ÷ 2

= $1,675 (unfavorable)

Direct labor efficiency variance = (Actual hour - Standard hour) × Standard price

= (8,900 × 28 ÷ 60 - 8,900 × 28 ÷ 60 ) × $100,800 ÷ 11,200 × 2

= 0

User Techvslife
by
8.5k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories