Answer:
Direct material quantity variance= $68,000 unfavorable
Step-by-step explanation:
Giving the following information:
Standard cost= $8.5 per pound
Standard quantity= 4 pounds per unit
Units produced= 61,000 units
Actual material= 252,000 pounds.
To calculate the direct material quantity variance, we need to use the following formula:
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (61,000*4 - 252,000)*8.5
Direct material quantity variance= (244,000 - 252,000)*8.5
Direct material quantity variance= $68,000 unfavorable
It is unfavorable because the company used more direct material to produce 61,000 units than estimated.