A company received a proposal for the development of a new software. While analyzing the specifications, it was found that there was no clear goal and the scope of the project could evolve. Which methodology should the company adopt to execute this project?

User Oddmund
by
5.3k points

1 Answer

0 votes

Answer:

Agile software development

Step-by-step explanation:

Agile software development was developed to provide faster software development and accommodate for changes in the software design. In this type of methodology, development teams can easily adapt to meet the new design of the software. The Agile methodology is suitable for projects where flexibility is desired to accommodate changes that can lead to the project evolving.