Answer:
Price variance $2,120 unfavorable
Quantity variance $ 19,998 Favorable
Step-by-step explanation:
Material price variance
A material price variance occurs where materials are purchased at a price either lower or higher than the standard price. A favorable variance is recorded where the actual total cost of materials is lower that the standard cost. While an adverse variance implies the opposite.
$
5,300 meters should have cost (5300×$19.80) = 104940
but did cost (actual cost -) = 107,060
Price variance 2120 unfavorable
Material quantity variance occurs when the actual quantity used to achieved a given level of output is more or less than the standard quantity.
It is determined by the difference between the actual and standard quantity of material for the actual level of output multiplied by the the standard price
pounds
Meters
Standard quantity allowed (9 × 690) 6210
Actual quantity 5,200
quantity variance (metres) 1010
Standard price × $19.80
Quantity variance $ 19,998 Favorable