Answer:
The correct answer is option (a) Less than 5% but more than 3%
Step-by-step explanation:
Scheduled time of project = 25
Calculating the activity variance, we have
Task Mean time Standard deviation Variance
A 4 0.6 0.6² = 0.36
B 5 0.2 0.2² = 0.04
E 2 0.1 0.1² = 0.01
F 6 1 1² = 1
H 2 0.2 0.2² = 0.04
M 6 0.1 0.1² = 0.01
Sum of variance = 0.36 +0.04 + 0.01 +1+ 0.04 + 0.01
=1.46
Standard deviation = √variance
=√1.46
=1.2083
probability that the project will be completed in 23 days or less
z = 23-25 /1.2083
= -1.65
which corresponds to prob. of 0.0494 = 4.94%
a is correct.