Answer:
2018: $78 million
2019: $468 million
2020: $234 million
Step-by-step explanation:
Given that State Construction incurred costs as follows:
Year Cost
2018 $60 million
2019 $360 million
2020 $180 million
Total cost = $60 million + $360 million + $180 million = $600 million
Percentage to total cost ratio is:
For 2018 = $60 million / $600 million = 0.1,
For 2019 = $360 million / $600 million = 0.6,
For 2020 = $180 million / $600 million = 0.3.
Revenue = Percentage to total cost ratio × Contract price.
Contract price = $780 million
For 2018, Revenue = 0.1 × $780 million = $78 million
For 2019, Revenue = 0.6 × $780 million = $468 million
For 2020, Revenue = 0.3 × $780 million = $234 million