Answer:
120 minutes
Explanation:
To solve this problem, you need to find the unit rate of each machine. The newer machine produces 20 cans per minute, while the older machine produces 15 cans per minute. Together, they produce 35 cans per minute. Dividing 4200 by 35, you get that it would take 120 minutes to produce that many cans.