110k views
3 votes
How much work is done by a crane that raises 2000 N of material a distance of 100 m

User Ppasler
by
4.0k points

2 Answers

6 votes

Answer: The work done by the crane is 200,000 Joules.

Explanation:

Hi, to answer this question we have to apply the work formula:

Work = force x distance

Replacing with the values given and solving for w:

W = 2000 N x 100 m = 200,000Nm = 200,000 Joules

In conclusion, the work done by the crane is 200,000 Joules.

Feel free to ask for more if needed or if you did not understand something.

User Etheryte
by
3.5k points
5 votes

Answer:


200,000J=2x10^5J

Explanation:

Since there are 2000N of material, the force needed to lift it must be equal to the weight of this material.

Force:
F=2000N

and the vertical distance that this material is moved:

Distance:
d=100m.

Now, to calculate the work done we use the following formula:


W=F*d

Where W is the work done, F is the force applied, and d is the distance moved.

Substituting the known values:


W=2000N*100m\\W=200,000J⇒This is the work done.

this quantity can also be expressed as follows:


W=2x10^5J

So, the work done by the crane is:
200,000J=2x10^5J

User Steve Rogers
by
3.6k points