Answer:
The answer is 72,000 Meters.
Step-by-step explanation:
From the question given, let us recall:
Moccasin Company produces cotton shirts. =12,000
The unit quantity standard = 6 meters
The quantity used actually was = 0.50 meters per shirt
The next step is to determine the quantity of cloth that should be used for the actual output of 12,000 shirts.
Quantity of cloth that should be used
= 12,000 * 6 meters cloth per shirt
= 72,000 Meters