530,539 views
36 votes
36 votes
A contractor on construction job specified a penalty for delay of completion beyond a certain date as: Rs.200 for the first day, Rs.250 for the second day, Rs300 for the third day and so on. The penalty for each succeeding day being Rs50 more than that of preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

Can someone tell me the answer of this??​

User MjZac
by
3.0k points

2 Answers

24 votes
24 votes

Answer :

  • Refer to the attachment

Additional Information :

  • Arithmetic progression (A.P.) is a sequence in which each term can be found by adding a certain quantity to its preceding term
  • Difference between two consecutive terms is called common difference
  • Progression means it's a type of sequence in which each term is related to its predecessor and successor.

A contractor on construction job specified a penalty for delay of completion beyond-example-1
A contractor on construction job specified a penalty for delay of completion beyond-example-2
User Vonovak
by
2.9k points
18 votes
18 votes

Answer:

  • Rs 27750

Explanation:

The penalty for each day forms a sequence

  • 200, 250, 300, ...

This is an AP with the first term of 200 and common difference of 50

The sum of the first 30 terms is


  • S_(30)=30*(a_1+a_(30))/2=15(200+200+29*50) = 27750
User Nitesh Verma
by
3.3k points