Answer:
a. Calculate the project's NPV and IRR where the discount rate is 11.2 percent. Is the project a worthwhile investment based on these two measures? Why or why not?
- NPV = -$4.5 million
- IRR = 2.97%
The project should be rejected because the NPV is negative.
b. Calculate the project's MIRR. Is the project a worthwhile investment based on this measure? Why or why not?
The project should be rejected because the NPV is negative. The IRR or MIRR do not matter at all if the NPV is negative.
Step-by-step explanation:
the net cash flows are:
- year 0 = -$18 million
- year 1 = $4.8 million
- year 2 = $4.8 million
- year 3 = $4.8 million
- year 4 = -$4.8 million
- year 5 = $1.4 million
- year 6 = $1.4 million
- year 7 = $1.4 million
- year 8 = $1.4 million
- year 9 = $1.4 million
- year 10 = $1.4 million
Using an excel spreadsheet we can determine the project's NPV and IRR:
NPV = $13.5 million - $18 million = -$4.5 million
IRR = 2.97%
We can also calculate MIRR using excel. We can use 11,2% finance rate and reinvestment rate:
MIRR = 8.57%