180k views
2 votes
This​ year, Hamilton, a local manufacturer of​ off-shore drilling​ platforms, entered into a contract to construct a drilling platform that will be placed in the North Atlantic Ocean. The total contract price is​ $5,000,000, and Hamilton estimates the total construction cost at​ $3,000,000. Actual costs incurred this year are​ $600,000. If Hamilton uses the percentage of completion​ method, the gross profit for this year is:

User SIMEL
by
4.5k points

1 Answer

6 votes

Answer:

$400,000

Step-by-step explanation:

Percentage completed:

$600,000/$3,000,000 20%

Hence:

Revenue $5,000,000 x .20 = $1,000,000

Less Costs to date (600,000)

Gross profit$ 400,000

Therefore If Hamilton uses the percentage of completion​ method, the gross profit for this year is: $400,000

User Trevor Nederlof
by
4.1k points