Answer:
$4785
Step-by-step explanation:
Estimated Production budget - 870 boxes
Hour /unit = 0.5
Total time required = (870*0.5)435 hr
Labor rate =$10/hr
Budgeted manufacturing overhead = 435 *10 *110%
=$4785