Defining the business needs for the project, assessing its importance to the company, and determining whether the project is actually feasible are all part of which phase of the system development life cycle (SDLC)?

a. analysis
b. design
c. planning
d. development

2 Answers

4 votes
The correct answer is c) planning
User Yariv Katz
by
3.6k points
2 votes

Answer:

C. Planning

Step-by-step explanation:

In the planning phase, project goals are determined and a high-level plan for the intended project is established. Planning is the most fundamental and critical organizational phase. The three primary activities involved in the planning phase are as follows:

1. Identification of the system for development

2.Feasibility assessment

3.Creation of project plan

Hope this helps!