Answer:
the standard cost to make one unit is $42
Step-by-step explanation:
Standard Costing is the Cost established from the firm`s Past experience.
Standard Costing Calculation for Concrete statues
Material
Concrete (10 pounds×$2) $20
Labor
Direct Labor( 0.2 direct labor hours × $30) $6
Overheads
Allocated ($80×0.2 direct labor hours) $16
Total $42