Answer:
$1,702,650
Step-by-step explanation:
The computation of the total manufacturing cost added to work in process is shown below:
Total manufacturing cost added to work in process
= Direct Materials + Direct Labor + Manufacturing Overhead applied
where,
Direct material $598,400
Direct labor is $520,000
And, the manufacturing overhead applied is
= Actual direct labor hours × predetermined overhead rate
= 41,000 hours × $14.25
= $584,250
So, the total manufacturing cost is
= $598,400 + $520,000 + $584,250
= $1,702,650
We simply applied the above formula