203k views
0 votes
M Corporation uses the weighted-average method in its process costing. The following data pertain to its Assembly Department for September. Percent Complete Units Materials Conversion Work in process, September 1 1,900 55 % 10 % Units started into production during September 9,300 Units completed during September and transferred to the next department 8,400 Work in process, September 30 2,800 75 % 25 % Required: Compute the equivalent units of production for both materials and conversion costs for the Assembly Department for September using the weighted-average method.

User Ulmangt
by
8.3k points

1 Answer

1 vote

Answer:

For material = 10,500 units

For conversion = 9,100 units

Step-by-step explanation:

The computation of the equivalent units of production for both materials and conversion costs is shown below:-

For material = Units completed and transferred to the next department + (Work in process × Material work in progress percentage

= 8,400 + (2,800 × 75%)

= 8,400 + 2,100

= 10,500 units

For conversion = Units completed and transferred to the next department + (Work in process × Conversion work in progress percentage

= 8,400 + (2,800 × 25%)

= 8,400 + 700

= 9,100 units

Therefore we have computed the equivalent units of production for both materials and conversion costs by applying the above formula.

User Charlotte Tan
by
9.1k points

No related questions found