Question
The complete question is as follows:
Machining Assembly
Direct Labour 16,000 12,000
Direct labour cost 20,000 15,000
Machine hours 5,000 1,000
Overhead($) 25,000 30,000
Answer
Machining Assembly
Overhead absorption rate = $5 per hour 200% of labour cost
Step-by-step explanation:
Overhead absorption rate is used to charged overheads to output achieved. It is calculated as follows:
OAR = Budgeted overhead / Budgeted activity
Machining Assembly
Overhead absorption rate 25,000/5000 hrs 30,000/15000 × 100
= $5 per hour 200% of labour cost