Answer:
Order quantity = 478units
Reorder point = 420 per week
Step-by-step explanation:
Given
Item cost =$8
Standard deviation of weekly demand = 20 per week
Order cost(C) = $207
Lead time = 3 weeks
Annual holding cost (H) = 24% of item cost
Service probability = 99%
Annual demand(D) = 27,400
Average demand = 548 per week
Order quantity = sqrt[(2 × D × C) ÷ H]
Order quantity = sqrt[(2 × 27400 × 207) ÷ (0.24 × 207)]
sqrt[ 11343600 ÷ 49.68]
= 477.84
Order quantity = 478 units
Reorder Point = Lead time × daily usage
21 × 20 = 420