Answer:
$13,915,000
Step-by-step explanation:
Land-cost $1,250,000
Construction cost $12,000,000
Equipment cost(150,000+15,000) $165,000
Inventory $500,000
Total initial investment outlay $13,915,000
Please note that fair value of land is irrelevant as the land was purchased for the outlet being set up and not for any other project.