Answer:
Total cost= $10,325
Step-by-step explanation:
Giving the following information:
Month Cost(Y) Hours(H)
January: $8,542 - 6,530
February: $7,750 - 5,950
March: $9,700 - 7,500
April: $7,435 - 5,700
May: $7,200 - 5,500
June: $9,263 - 6,750
To calculate the total cost under the high-low method, we need to use the following formulas:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (9,700 - 7,200) / (7,500 - 5,500)
Variable cost per unit= $1.25 per hour
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 9,700 - (1.25*7,500)= $325
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 7,200 - (1.25*5,500)= $325
Now, for 8,000 hours:
Total cost= 325 + 1.25*8,000= $10,325