Answer:
$5,000
Step-by-step explanation:
Consequential damages are damages that result from the one party in a contract not performing their part or breaching the contract.
In this case, New Data can sue Mona for consequential damages resulting from Mona not performing her contractual obligations. The damages that New Data can recover = $5,000 which is the profit from the lost sale. The $1,000 spent fixing the computer cannot be recovered.