Answer: C. The loss of profit from delayed opening.
Explanation: Tile and Grout failed to execute the job they were contracted and caused water world to delay opening. In business Tile and Grout company will be held liable for failure to execute contract.
Water world can recover the loss of profit from delayed opening due to the failure in the part of Tile and Grout company.