Answer:
Total job costs added in October $ 19,000
Step-by-step explanation:
Computations
Job costs added to Work in Process inventory for October
Direct materials $ 4,000
Direct labor $ 7,500
Overhead at 100 % of Direct Labor costs $ 7,500
Total job costs added in October $ 19,000