Answer:
The rate charged per hour of labor is 120.
Step-by-step explanation:
Rate charged per hour of labor is given by:
= Budgeted cost per labor hour + Profit margin
= 660000/10000 + 54
= 120
Therefore, The rate charged per hour of labor is 120.