The MRP input stating which end items are to be produced, when they are needed, and what quantities are needed, is the: A. bill of materials. B. net requirements chart. C. master schedule. D. assembly time chart. E. inventory records.

User Rwfbc
by
5.9k points

1 Answer

1 vote

Answer:

C. master schedule.

Step-by-step explanation:

Master schedule: It is defined as detailed planning in the manufacturing process that includes which item needs to be produced, how much to be produced, staffing, inventory management, etc. It also suggests steps track manufacturing output in fulfilling the demand of the customer. It acts as a blueprint in achieving the company's vision.

MRP is Material requirements planning, which is used to determine how many materials to be ordered for one particular item.