Answer:
The correct answer is 63,200 kg.
Step-by-step explanation:
According to the scenario, the computation of the given data are as follows:
Raw material required for production = Production in units × req. raw material per unit
= 16,000 units × 4 kg
= 64,000 kg.
Beginning inventory = (64,000 kg) × 10%
= 6,400 kg
Ending inventory = ( 14,000 × 4 kg) × 10%
= 56,000 kg × 10%
= 5,600 kg
So, we can calculate the budgeted purchases of raw materials by using following formula:
Budgeted purchases of raw materials = Raw material required for production + Ending inventory - Beginning inventory
= 64,000 kg + 5,600 kg - 6,400 kg
= 63,200 kg