157k views
3 votes
You are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely estimate of 15 days and optimistic estimate of 12 days. What is the mean using the PERT technique?

a.18 days
b.25.5 days
c.15 days
d.16 days

User PaulG
by
5.7k points

1 Answer

5 votes

Answer: d.16 days

Explanation:

Hi, using PERT technique we can calculate the mean by applying the next formula:

Mean = (a + 4m + b)/6

Where:

a = optimistic time

m = most likely time

b = pessimistic time

Replacing with the values given:

Mean = (12 +4 (15) + 24)/6

Solving

m = (12+ 60+24)/6

m= 96/6

m = 16 days

Feel free to ask for more if needed or if you did not understand something.

User Swader
by
6.3k points