Answer:
a. The cutoff value for investigation if the controller’s rule of thumb is to investigate all variances equal to or greater than 6 percent of standard cost is $2,280.
b.The month that will have their direct-labor efficiency variance investigated will be the month of since june variance is 2,400 and hence is above $2,280.
Step-by-step explanation:
According to the given data, the standard direct-labor cost during each of these months was $38,000, therefore, in order to calculate the cutoff value for investigation, we would have make the following calculation:
Cutoff value for investigation =6% of Standard cost =$38,000 *6% =$2,280
The month that will have their direct-labor efficiency variance investigated will be the month of since june variance is 2,400 and hence is above $2,280.